NOTICE OF UPCOMING WORK AND TRAFFIC IMPACTS

NOTICE OF UPCOMING WORK AND TRAFFIC IMPACTS

BNSF SR 20 RAILROAD TRESTLE WORK

APRIL 4, 2024

This notice regards temporary traffic impacts for the above project for SR 20 near Metcalf Street

BNSF crews will be performing work on the trestle crossing over SR 20 west of Metcalf Street on April 9 and 10, 2024 between 7 AM and 3 PM each day.

During those work hours, SR 20 will be limited to one lane of traffic between Metcalf Street and Patrick Street. During each of the days there may be temporary traffic holds, for up to 20 minutes, while BNSF crews work on the trestle over the highway.

Traffic control will be set up and flaggers will be on site. SR 20 will be opened to two-way traffic at the end of each day.

Please feel free to contact David Lee, City Engineer at 360-855-3219 or by email dlee@sedro-woolley.gov  with any questions you might have. 